There are big changes happening on campus! Here is the latest...
†
? The Student Services/Administration building has been vacated to prepare for construction
? The Vice President for Student and Outreach Services and the Executive Vice President for Instruction have moved to the Humanities Building
? Most†?public-facing?†services†[students, prospects, etc.]†have moved to the new Humanities Multipurpose Room
? The Vice President for Administrative Services has moved to the Business Technology building, along with most of the ?back-office? administrative support functions
? The President's Office, Development, Marketing and Human Resources have moved into their new location in LRC
? The south side of the SUB will be CLOSED beginning next week. Only half of the space will be available due to construction.
? Work will soon begin on the Student Services building.
†